On June 28, the first batch of 8 sets of equipment of rubber-tyred gantry crane (RTGs) project of Maersk India GTI contracted by ZPMC set sail for shipment.
There is a total of 11 sets RTGs in the project, which commenced on June 24, 2020, with the manufacturing cycle of only 8 months. The project department has strictly controlled the whole process plan to ensure the steady progress of the project and complete the commissioning and test run as planned. Near the time of delivery, continuous rainy weather makes it more difficult to finish the whole machine painting. The project department carefully organized the construction and inspection in the weather window period, and finally ensures that the goods are delivered with zero rectification. Currently, the second batch of the 3 RTGs of the project has entered the commissioning stage.