Recently, "ZPMC 26" set sail slowly with 4 quay cranes including Evergreen (Los Angeles), Evergreen (Auckland) and Port of Prince of Canada to user terminals.
2 quay cranes of Evergreen (Los Angeles) and 1 quay crane of Changrong (Auckland) belong to Evergreen Marine Corporation's new container terminal project in the United States. The 3 quay cranes have a rated load of 61t and a lifting height of 52m. The Auckland project requires the lowering of the quay crane to be transported through the Golden Gate Bridge in San Francisco and the Auckland Bay Bridge.
The one for the Port of Prince of Canada has a rated load of 70t and a lifting height of 52m.
During the delivery, the Project Department overcomes many unfavorable factors such as site, personnel and weather, actively communicates with supervising users, rationally adjusts production plan, and properly carry out quality control of product process, which has been fully affirmed and strongly supported by supervising company, and finally ensures smooth shipment of the three quay cranes.