delivered one STS successfully to Australia Fremantle Terminal of Patrick Group
on April 28th.
The STS
was unloaded on Dec. 27th, 2019, when was the holiday of Christmas
and New Year Day then. The project team completed the unloading successfully
with the assistance of the user and local subcontractors. The project team
started the common 24h durability test on Jan. 25th, 2020, when it
was the holiday of Spring Festival of China. The project team completed the
test in time, despite the homesick.
The
Company failed to send the anti-collision limit of the beam due to the impact
of the pandemic. The project team made positive coordination with the user for
a limit from other terminals finally and started the 200h durability test on
March 4th, after the installation and debugging. The user’s
requirements on the pandemic control only allowed two engineers were working
together on the site. However, the project team completed the delivery finally
with the common hard work of the team.