Shipment of the Fifth Batch of Equipment for Singapore Automated Rail-Mounted Gantry Crane Project
time:2021/03/31 00:00:00
On March 28, the "ZHEN HUA 25" shipped six automated rail-mounted gantry cranes for the Tuas wharf of PSA Singapore from Wharf of Nantong with a wheel loader to Singapore port of Tuas wharf.
In the Project, there are 56 large single cantilever rail-mounted gantry cranes, which are specially designed by ZPMC to match the new layout of Tuas wharf. With the most advanced control technology and design scheme, the rail-mounted gantry crane has the automatic operation function of the exchange area at the end of the yard, so that the exchange area of the rail-mounted gantry crane at the end of the yard has the automatic operation capacity of the external truck.
At present, the six automated rail-mounted gantry cranes in the sixth batch have been in the stage of final assembly and commissioning, and are planned to be shipped in early May.