unloading team completed the 3-day unloading of 4 pieces of the port machinery
equipment for DPW Ecuador Posja Terminal after the hard work on May 5th.
Fabio, Manager of Terminal Engineering Department, made high praise for the
effective work of the unloading team on the site with the thumb high.
Zhenhua
No. 19 loaded with one STS and 3 RTGs arrived at the open seas ofEcuadorat the
beginning of April, waiting for berthing.Ecuadorstopped all flights and
made strict curfew due to the pandemic, which was a huge challenge to the
unloading and delivery of the equipment.
To
make sure the timely unloading of the equipment after the barge berthing, ZPMC
made allocation of overseas resources. Fanyong, the shipping technician and
Wangquan, the unloading commander, of the project inDominicaarrived at the site. They
founded an unloading team of 4 members, including Jianglei, STS delivery
director and Zhang Xinyu, RTG delivery director, who had arrived at the site
earlier. They prepared the training plan in advance and provided the training
on the subcontractor’s workers, making highly effective preparations for the
unloading.
They
made many negotiations with the user who provided a 3-day berthing period for
Zhenhua No. 19. The barge would leave the port for the next berthing period in
case of failing to complete the unloading. The unloading team prepared detailed
operation procedures on the basis of the unloading plan provided by the
shipping department of the Company and started the unloading at 3:00 in the
early morning of May 2nd. Finally, the unloading team completed the
work within the stipulated period with the scientific allocation and the
support from the terminal user.